Tainter Gate Cable Replacement (and Drawdown) Lake Red Rock Marion County, Iowa

Environmental Assessment Decision

On February 8, 2005, a Finding of No Significant Impact (FONSI) was signed by the Corps of Engineers for the project, as proposed in the Environmental Assessment, and summarized below. The Statement of Findings (SOF) summarizes the public involvement, public review comments, the preferred alternative, and includes the FONSI. This package is available below. One comment letter did prompt a further review of the effect of the drawdown on local area shallow wells. The examination of the existing data concluded that municipal wells upstream of the dam should not be significantly affected by the 10-foot drawdown. Of the public municipal wells where the installation date is known, none are expected to be reduced to an inadequate pumping level, although there may be minor reductions in some well capacities.

This information and analysis has been compiled into a report entitled, “ Lake Red Rock Groundwater Well Analysis for Tainter Gate Repair Drawdown”, dated January 2005. This report is an attachment to this SOF package. As a result of the EA and subsequent groundwater well investigation, no significant impacts resulting from the implementation of the project have been identified.

Statement of Finding Package:

Title Size Posted On
Statement of Finding 170 KB 02-09-2005
FONSI 62 KB 02-09-2005
Ground Water Well Analysis 1 MB 02-09-2005
US Fish and Wildlife Conversation Record 22 KB 02-09-2005
Letter from Carlisle Water Department 62 KB 02-09-2005
         Corps Response to Letter 54 KB 02-09-2005

Environmental Assessment

Summary:

The Rock Island District of the U.S. Army Corps of Engineers (District) has prepared the Environmental Assessment (EA) and draft Finding of No Significant Impact (FONSI) addressing the tainter gate cable replacement at Lake Red Rock, Marion County, Iowa. The purpose of this EA was to assess the impacts associated with the dewatering the tainter gate bays, replacement of the tainter gate lifting cables, as well as touch-up painting of the gates, and periodic inspection and maintenance of the dam.

The District originally scheduled the work to begin in September 2007, yet high water in 2007 and 2008 has delayed the project.

At the current elevation of the conservation pool, the tainter gate cables and brackets are permanently submerged, making performance of scheduled repair and maintenance on the tainter gates and lifting cables virtually impossible without dewatering the tainter gate bays. The District proposes a one time 10-foot drawdown and performance of the scheduled repair and maintenance to the tainter gates and cables during the fall of 2007, with future installation of a traveling bulkhead system.

The District will lower the lake at a rate of 0.5 feet per day, completing the drawdown in 20 days. The estimated time for cable replacement and touch-up painting is 4 to 7 weeks. When the District completes the work it will raise the pool as quickly as possible, while still maintaining outflows of at least 300 cubic feet per second. The District anticipates the lake will resume its conservation pool elevation in approximately 54 days. The project will take approximately 3.4 to 4 months to complete under ideal conditions; however, the time to raise the pool is entirely weather dependent.

The primary purpose of the drawdown is to replace the cables on the dam tainter gates. During the flood of 2008, the existing cables performed well and will remain in service until other 2008 flood recovery work is accomplished.

This EA evaluated the alternatives and assessed the impacts of the preferred alternative. This tainter gate maintenance will ensures the long-term project purpose of flood control is maintained at the current levels, without any reduction in the life, health, and safety to local and regional human populations.

 

Copies of the Environmental Assessment are available at the following locations:

Area Post Offices:

Melcher, Harvey, Eddyville, Hamilton, Lacona, Dallas Center, Pella, Pershing, Knoxville, Cumming, Ottumwa, Bussey, Columbia, Swan

Area Libraries:

Pella (public and Central College), Ottumwa (public and Indian Hills Community College), Knoxville (public)

Public Review and Comment Period:

The 30-day public review and comment period ended on September 25, 2004.

Report Files:

Title Size Posted On
Report Cover Letter 85 KB 08-24-2004
Executive Summary 30 KB 08-24-2004
Table of Contents 22 KB 08-24-2004
Environmental Assessment 353 KB 08-24-2004
Draft FONSI 18 KB 08-24-2004
Figure 1. Location and plan view of Red Rock Dam 53 KB 08-24-2004
Figure 2. Red Rock Reservoir depth at elevation 732 NGVD 238 KB 08-24-2004
Figure 3. Lake Red Rock project area with conservation pool, proposed drawdown pool, and areas exposed by drawdown 201 KB 08-24-2004
Figure 4. Lake Red Rock pool elevation average based on data from 1994-2003 24 KB 08-24-2004
Appendix A - Coordination 4218 KB 08-24-2004
Appendix B - Distribution List 93 KB 08-24-2004
Appendix C - Construction procedures for tainter gate cable replacement 105 KB 08-24-2004
Appendix D - Construction procedures for tainter gate painting 136 KB 08-24-2004
Appendix E - Construction procedures for installation of the bulkhead system 31 KB 08-24-2004

 

Contact Us | Privacy & Security | Disclaimers | Site Feedback

2004 Rock Island District, US Army Corps of Engineers
Rock Island District is part of the Mississippi Valley Division of the U.S. Army Corps of Engineers, Department of Army

For questions about the Rock Island District, email or call: CEMVR-CC@usace.army.mil at 309-794-4200 or FAX: 309-794-5793

U.S. Army Engineer District, Rock Island
Box 2004
Clock Tower Building #205
1500 Rock Island Drive
Rock Island, Illinois 61204-2004

Mailing and Driving Directions

For webmaster related comments, improvements, usability, accessibility of this site - email: WebManager@usace.army.mil